Dept. of Trans. PROGRESS Serial No. Contract No. 19-263-08-18 08-388524 PROGRESS PAYMENT VOUCHER %complete: %time: 44% 71% Location: Federal Project: 08-SBD-330-32.3/32.6 B1ST-S330(12) 08-SBD-330-33.4/33.8 Progress payment No. 005 Payment period ending: 09-20-19 O'DONNELL CONSTRUCTION, INC. 559 W. COVINA BLVD SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,009,352.80 267,616.40 2. a. Extra Work 9,427.01 0.00 b. Adustment Comp. 62,413.91 0.00 3. Materials on Hand 58,480.66 0.00 4. Earned Subject to Retention 1,139,674.38 267,616.40 5. Mobilization 266,000.00 0.00 6. Total Work Completed 1,347,193.72 7. Deductions -10,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,395,674.38 277,616.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 277,616.40