Dept. of Trans. PROGRESS Serial No. Contract No. 03-023-14-11 08-4047U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 8% 08-SBD-15-R137.0/163.3 Federal Project: ACIM-015-3(39) ACIM-015-3(39) Progress payment No. 04 Payment period ending: 01-17-03 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01986 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,455,885.94 779,130.55 2.a. Extra Work 3,496.00 0.00 b. Adjustment Comp. 3. Materials on Hand 129,855.00 27,185.00 4. Earned Subject to Retention 2,589,236.94 806,315.55 5. Mobilization 2,241,200.00 2,241,200.00 6. Total Work Completed 4,700,581.94 7. Deductions -57,031.60 -57,031.60 8. a.Contract Retentions -258,923.69 -80,631.55 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,514,481.65 2,909,852.40 10. Reduction Amt to Escrow 11. Payment to Escrow 100,000.00 12. Net Pymt. this Estimate 2,909,852.40