Dept. of Trans. PROGRESS Serial No. Contract No. 03-335-09-53 08-4047U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 59% 08-SBD-15-R137.0/163.3 Federal Project: ACIM-015-3(39) ACIM-015-3(39) Progress payment No. 18 Payment period ending: 11-20-03 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01986 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,099,690.90 1,457,144.15 2.a. Extra Work 635,212.67 41,214.46 b. Adjustment Comp. 6,580.42 0.00 3. Materials on Hand 223,771.23 -0.08 4. Earned Subject to Retention 25,965,255.22 1,498,358.53 5. Mobilization 4,482,400.00 0.00 6. Total Work Completed 30,223,883.99 7. Deductions -1,125,149.24 -364,286.04 8. a.Contract Retentions -1,298,262.76 -74,917.93 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 28,024,243.22 1,059,154.56 10. Reduction Amt to Escrow 11. Payment to Escrow 1,298,260.00 12. Net Pymt. this Estimate 1,059,154.56