Dept. of Trans. PROGRESS Serial No. Contract No. 04-026-10-35 08-4047U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 68% 64% 08-SBD-15-R137.0/163.3 Federal Project: ACIM-015-3(39) ACIM-015-3(39) Progress payment No. 20 Payment period ending: 01-20-04 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01986 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,770,365.47 187,874.50 2.a. Extra Work 793,700.90 125,735.59 b. Adjustment Comp. -100,323.08 -106,903.50 3. Materials on Hand 212,916.53 -30,457.34 4. Earned Subject to Retention 27,676,659.82 176,249.25 5. Mobilization 4,482,400.00 0.00 6. Total Work Completed 31,946,143.29 7. Deductions -125,063.20 -4,000.00 8. a.Contract Retentions -1,383,832.99 -8,812.46 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 30,650,163.63 163,436.79 10. Reduction Amt to Escrow 11. Payment to Escrow 1,383,830.00 12. Net Pymt. this Estimate 163,436.79