Dept. of Trans. SEMI-FINAL Serial No. Contract No. 04-344-13-49 08-4047U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-SBD-15-R137.0/163.3 Federal Project: ACIM-015-3(39) ACIM-015-3(39) Progress payment No. 32 Payment period ending: 09-08-04 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01986 Total Estimate This Estimate 1. Contract Itms Without Mobil. 42,721,706.70 14,443.24 2.a. Extra Work 1,269,067.74 0.00 b. Adjustment Comp. 718,018.14 4,280.00 3. Materials on Hand 4. Earned Subject to Retention 44,708,792.58 18,723.24 5. Mobilization 4,482,400.00 0.00 6. Total Work Completed 49,191,192.58 7. Deductions -6,450.00 10,000.00 8. a.Contract Retentions -2,207,632.57 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 2,207,632.57 0.00 9. Total pay to Contractor 49,184,742.58 28,723.24 10. Reduction Amt to Escrow -2,207,630.00 0.00 11. Payment to Escrow 2,207,630.00 12. Net Pymt. this Estimate 28,723.24