Dept. of Trans. PROGRESS Serial No. Contract No. 02-358-15-52 08-4221U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 47% 47% 08-RIV-91-17.4/21.6 Federal Project: ACNH-P091(105) Progress payment No. 14 Payment period ending: 12-20-02 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA, CA 92083-8831 Escrow No. 01894 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,927,612.28 454,417.87 2.a. Extra Work 1,221,067.03 16,215.37 b. Adjustment Comp. 42,074.63 -19,885.91 3. Materials on Hand 189,679.40 -88,986.00 4. Earned Subject to Retention 6,380,433.34 361,761.33 5. Mobilization 1,320,500.00 0.00 6. Total Work Completed 7,511,253.94 7. Deductions -308.52 0.00 8. a.Contract Retentions -319,021.67 -18,088.07 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,381,603.15 343,673.26 10. Reduction Amt to Escrow 11. Payment to Escrow 319,020.00 12. Net Pymt. this Estimate 343,673.26