Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 03-034-08-24 08-4221U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 49% 48% 08-RIV-91-17.4/21.6 Federal Project: ACNH-P091(105) Progress payment No. 16 Payment period ending: 01-17-03 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA, CA 92083-8831 Escrow No. 01894 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,156,574.08 40,613.10 2.a. Extra Work 1,239,650.89 10,087.71 b. Adjustment Comp. 42,074.63 0.00 3. Materials on Hand 189,679.40 0.00 4. Earned Subject to Retention 6,627,979.00 50,700.81 5. Mobilization 1,320,500.00 0.00 6. Total Work Completed 7,758,799.60 7. Deductions -308.52 0.00 8. a.Contract Retentions -331,398.95 -2,535.04 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,616,771.53 48,165.77 10. Reduction Amt to Escrow 11. Payment to Escrow 331,390.00 12. Net Pymt. this Estimate 48,165.77