Dept. of Trans. PROGRESS Serial No. Contract No. 03-113-13-44 08-4221U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 60% 60% 08-RIV-91-17.4/21.6 Federal Project: ACNH-P091(105) Progress payment No. 19 Payment period ending: 04-18-03 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA, CA 92083-8831 Escrow No. 01894 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,766,186.93 714,553.52 2.a. Extra Work 1,347,680.33 4,833.17 b. Adjustment Comp. 57,702.02 0.00 3. Materials on Hand 175,089.82 -35,128.01 4. Earned Subject to Retention 8,346,659.10 684,258.68 5. Mobilization 1,390,000.00 0.00 6. Total Work Completed 9,561,569.28 7. Deductions -13,326.02 0.00 8. a.Contract Retentions -417,332.96 -34,212.94 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,306,000.12 650,045.74 10. Reduction Amt to Escrow 11. Payment to Escrow 417,330.00 12. Net Pymt. this Estimate 650,045.74