Dept. of Trans. PROGRESS Serial No. Contract No. 03-143-10-26 08-4221U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 65% 64% 08-RIV-91-17.4/21.6 Federal Project: ACNH-P091(105) Progress payment No. 20 Payment period ending: 05-20-03 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA, CA 92083-8831 Escrow No. 01894 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,595,183.31 828,996.38 2.a. Extra Work 1,431,113.85 83,433.52 b. Adjustment Comp. 57,702.02 0.00 3. Materials on Hand 130,323.51 -44,766.31 4. Earned Subject to Retention 9,214,322.69 867,663.59 5. Mobilization 1,390,000.00 0.00 6. Total Work Completed 10,473,999.18 7. Deductions -13,516.01 -189.99 8. a.Contract Retentions -460,716.13 -43,383.17 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,130,090.55 824,090.43 10. Reduction Amt to Escrow 11. Payment to Escrow 460,710.00 12. Net Pymt. this Estimate 824,090.43