Dept. of Trans. PROGRESS Serial No. Contract No. 03-297-11-13 08-4221U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 87% 08-RIV-91-17.4/21.6 Federal Project: ACNH-P091(105) Progress payment No. 25 Payment period ending: 10-20-03 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA, CA 92083-8831 Escrow No. 01894 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,515,372.98 754,904.53 2.a. Extra Work 1,529,447.52 7,687.72 b. Adjustment Comp. 210,559.56 0.00 3. Materials on Hand 0.00 -211,155.86 4. Earned Subject to Retention 13,255,380.06 551,436.39 5. Mobilization 1,390,000.00 0.00 6. Total Work Completed 14,645,380.06 7. Deductions -24,916.01 0.00 8. a.Contract Retentions -662,769.00 -27,571.82 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,957,695.05 523,864.57 10. Reduction Amt to Escrow 11. Payment to Escrow 662,760.00 12. Net Pymt. this Estimate 523,864.57