Dept. of Trans. FINAL Serial No. Contract No. 05-216-15-18 08-4221U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-RIV-91-17.4/21.6 Federal Project: ACNH-P091(105) Progress payment No. 45 Payment period ending: 01-20-05 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA, CA 92083-8831 Escrow No. 01894 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,766,776.00 0.00 2.a. Extra Work 1,794,898.87 10,725.33 b. Adjustment Comp. 324,413.81 10,000.00 3. Materials on Hand 4. Earned Subject to Retention 14,886,088.68 20,725.33 5. Mobilization 1,390,000.00 0.00 6. Total Work Completed 16,276,088.68 7. Deductions -25,327.25 0.00 8. a.Contract Retentions -736,227.63 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 736,227.63 0.00 9. Total pay to Contractor 16,250,761.43 20,725.33 10. Reduction Amt to Escrow -736,220.00 0.00 11. Payment to Escrow 736,220.00 12. Net Pymt. this Estimate 20,725.33