Dept. of Trans. PROGRESS Serial No. Contract No. 09-296-14-33 08-422204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 30% 24% 08-RIV-78-3.3/ .0 Federal Project: SARR-P078(108) A-P078(108) Progress payment No. 02 Payment period ending: 10-20-09 WESTERN STRUCTURES 6005 TYLER STREET RIVERSIDE CA 92503 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 267,942.91 196,650.64 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 267,942.91 196,650.64 5. Mobilization 33,250.00 15,750.00 6. Total Work Completed 301,192.91 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 301,192.91 212,400.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 212,400.64