Dept. of Trans. PROGRESS Serial No. Contract No. 00-299-10-13 08-4281U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 66% 08-RIV-86-R2.4/R10.8 Federal Project: ACNH-P086(58) Progress payment No. 21 Payment period ending: 10-20-00 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01212 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,099,144.00 852,851.25 2.a. Extra Work 2,328,790.97 28,141.98 b. Adjustment Comp. 313,143.27 28,463.63 3. Materials on Hand 132,991.78 0.00 4. Earned Subject to Retention 22,874,070.02 909,456.86 5. Mobilization 600,342.00 0.00 6. Total Work Completed 23,341,420.24 7. Deductions -1,866.25 0.00 8. a.Contract Retentions -1,143,703.50 -45,472.84 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 22,328,842.27 863,984.02 10. Reduction Amt to Escrow 11. Payment to Escrow 1,143,700.00 12. Net Pymt. this Estimate 863,984.02