Dept. of Trans. PROGRESS Serial No. Contract No. 01-024-08-01 08-4281U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 75% 08-RIV-86-R2.4/R10.8 Federal Project: ACNH-P086(58) Progress payment No. 24 Payment period ending: 01-20-01 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01212 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,738,969.47 978,959.31 2.a. Extra Work 2,495,077.64 16,397.97 b. Adjustment Comp. 213,043.75 -100,099.52 3. Materials on Hand 88,810.92 -44,180.86 4. Earned Subject to Retention 28,535,901.78 851,076.90 5. Mobilization 600,342.00 0.00 6. Total Work Completed 29,047,432.86 7. Deductions -1,866.25 0.00 8. a.Contract Retentions -1,426,795.09 -42,553.85 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 27,707,582.44 808,523.05 10. Reduction Amt to Escrow 11. Payment to Escrow 1,300,000.00 12. Net Pymt. this Estimate 808,523.05