Dept. of Trans. PROGRESS Serial No. Contract No. 03-143-11-16 08-4353U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 76% 93% 08-RIV-91-7.4/21.6 Federal Project: ACNH-P091(104) Progress payment No. 24 Payment period ending: 05-20-03 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 429 FONTANA CA 92334 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,788,348.59 621,641.54 2.a. Extra Work 473,557.52 -1,016.41 b. Adjustment Comp. 195,297.04 0.00 3. Materials on Hand 353,338.15 50,463.35 4. Earned Subject to Retention 11,810,541.30 671,088.48 5. Mobilization 1,650,000.00 0.00 6. Total Work Completed 13,107,203.15 7. Deductions -25,309.28 8,200.00 8. a.Contract Retentions -590,527.07 -33,554.43 b. Unsatisfactory Prog. -196,246.34 -33,554.42 c. Reduction after 95% Comp. 9. Total pay to Contractor 12,648,458.61 612,179.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 612,179.63