Dept. of Trans. PROGRESS Serial No. Contract No. 08-269-11-02 08-4393U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 38% 26% 08-SBD-15-169.8/181.9 Federal Project: ACIM-015-3(42) Progress payment No. 08 Payment period ending: 09-19-08 LAS VEGAS PAVING CORPORATION 4420 S DECATUR BLVD LAS VEGAS NV 89103 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,408,486.49 3,811,167.03 2.a. Extra Work 248,893.92 94,891.44 b. Adjustment Comp. 1,177,132.62 547,238.38 3. Materials on Hand 486,197.05 76,825.76 4. Earned Subject to Retention 17,320,710.08 4,530,122.61 5. Mobilization 6,270,000.00 0.00 6. Total Work Completed 23,104,513.03 7. Deductions -749,848.21 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 22,840,861.87 4,540,122.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,540,122.61