Dept. of Trans. PROGRESS Serial No. Contract No. 09-239-13-09 08-4393U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 46% 08-SBD-15-169.8/181.9 Federal Project: ACIM-015-3(42) Progress payment No. 20 Payment period ending: 08-20-09 LAS VEGAS PAVING CORPORATION 4420 S DECATUR BLVD LAS VEGAS NV 89103 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 46,970,217.67 2,934,366.08 2.a. Extra Work 1,152,514.63 32,562.31 b. Adjustment Comp. 2,077,286.89 -32,219.32 3. Materials on Hand 146,219.09 -19,325.97 4. Earned Subject to Retention 50,346,238.28 2,915,383.10 5. Mobilization 6,600,000.00 0.00 6. Total Work Completed 56,800,019.19 7. Deductions -789,050.75 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 56,157,187.53 2,915,383.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,915,383.10