Dept. of Trans. PROGRESS Serial No. Contract No. 09-296-14-33 08-4393U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 58% 08-SBD-15-169.8/181.9 Federal Project: ACIM-015-3(42) Progress payment No. 22 Payment period ending: 10-20-09 LAS VEGAS PAVING CORPORATION 4420 S DECATUR BLVD LAS VEGAS NV 89103 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 52,320,475.37 2,649,614.08 2.a. Extra Work 1,256,677.46 80,813.36 b. Adjustment Comp. 2,116,410.83 -16,876.06 3. Materials on Hand 103,123.48 -24,775.89 4. Earned Subject to Retention 55,796,687.14 2,688,775.49 5. Mobilization 6,600,000.00 0.00 6. Total Work Completed 62,293,563.66 7. Deductions -789,050.75 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 61,607,636.39 2,688,775.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,688,775.49