Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 10-279-13-49 08-4393U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-SBD-15-169.8/181.9 Federal Project: ACIM-015-3(42) Progress payment No. 32 Payment period ending: 09-24-10 LAS VEGAS PAVING CORPORATION 4420 S DECATUR BLVD LAS VEGAS NV 89103 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 54,197,538.00 0.00 2.a. Extra Work 1,729,748.51 0.00 b. Adjustment Comp. 2,438,150.85 0.00 3. Materials on Hand 4. Earned Subject to Retention 58,365,437.36 0.00 5. Mobilization 6,600,000.00 0.00 6. Total Work Completed 64,965,437.36 7. Deductions -30,400.00 768,650.75 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 64,935,037.36 768,650.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 768,650.75