Dept. of Trans. PROGRESS Serial No. Contract No. 06-144-17-07 08-443614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 72% 08-SBD-210-R12.7/R15.2 Federal Project: NONE Progress payment No. 03 Payment period ending: 05-20-06 T D S ENGINEERING 2899 AGOURA ROAD SUITE 171 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 424,957.61 157,857.25 2.a. Extra Work b. Adjustment Comp. -22,925.00 -22,925.00 3. Materials on Hand 0.00 -11,115.00 4. Earned Subject to Retention 402,032.61 123,817.25 5. Mobilization 6. Total Work Completed 402,032.61 7. Deductions 8. a.Contract Retentions -20,101.63 -6,190.86 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 381,930.98 117,626.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 117,626.39