Dept. of Trans. PROGRESS Serial No. Contract No. 06-174-08-05 08-443614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 82% 08-SBD-210-R12.7/R15.2 Federal Project: NONE Progress payment No. 04 Payment period ending: 06-20-06 T D S ENGINEERING 2899 AGOURA ROAD SUITE 171 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 467,453.61 42,496.00 2.a. Extra Work b. Adjustment Comp. -22,925.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 444,528.61 42,496.00 5. Mobilization 6. Total Work Completed 444,528.61 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions -22,226.43 -2,124.80 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 417,302.18 35,371.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 35,371.20