Dept. of Trans. PROGRESS Serial No. Contract No. 03-358-09-44 08-4437U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 25% 31% 08-SBD-210-R13.5/R17.0 Federal Project: ACNH-S210(4) Progress payment No. 06 Payment period ending: 12-19-03 RIVERSIDE CONSTRUCTION COMPANY INC P O BOX 1146 RIVERSIDE CA 92502 Escrow No. 02106 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,642,070.86 1,541,581.10 2.a. Extra Work 110,269.07 12,242.72 b. Adjustment Comp. 3. Materials on Hand 394,943.38 275,857.46 4. Earned Subject to Retention 6,147,283.31 1,829,681.28 5. Mobilization 712,500.00 150,000.00 6. Total Work Completed 6,464,839.93 7. Deductions 8. a.Contract Retentions -501,577.01 -69,816.81 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,358,206.30 1,909,864.47 10. Reduction Amt to Escrow 11. Payment to Escrow 501,570.00 12. Net Pymt. this Estimate 1,909,864.47