Dept. of Trans. PROGRESS Serial No. Contract No. 04-267-11-00 08-4437U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 71% 78% 08-SBD-210-R13.5/R17.0 Federal Project: ACNH-S210(4) Progress payment No. 15 Payment period ending: 09-20-04 RIVERSIDE CONSTRUCTION COMPANY INC P O BOX 1146 RIVERSIDE CA 92502 Escrow No. 02106 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,162,327.42 927,108.88 2.a. Extra Work 425,789.15 181,515.82 b. Adjustment Comp. 56,291.40 0.00 3. Materials on Hand 187,088.35 -48,693.58 4. Earned Subject to Retention 18,831,496.32 1,059,931.12 5. Mobilization 750,000.00 0.00 6. Total Work Completed 19,394,407.97 7. Deductions -17,096.25 -1,160.58 8. a.Contract Retentions -941,574.82 -52,996.56 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,622,825.25 1,005,773.98 10. Reduction Amt to Escrow 11. Payment to Escrow 941,570.00 12. Net Pymt. this Estimate 1,005,773.98