Dept. of Trans. SEMI-FINAL Serial No. Contract No. 05-258-14-57 08-4437U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-SBD-210-R13.5/R17.0 Federal Project: ACNH-S210(4) Progress payment No. 24 Payment period ending: 03-11-05 RIVERSIDE CONSTRUCTION COMPANY INC P O BOX 1146 RIVERSIDE CA 92502 Escrow No. 02106 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,538,659.44 2,318.00 2.a. Extra Work 905,739.97 25,174.02 b. Adjustment Comp. 257,608.45 0.00 3. Materials on Hand 4. Earned Subject to Retention 26,702,007.86 27,492.02 5. Mobilization 750,000.00 0.00 6. Total Work Completed 27,452,007.86 7. Deductions -40,772.12 0.00 8. a.Contract Retentions -1,316,419.78 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 1,316,419.78 0.00 9. Total pay to Contractor 27,411,235.74 27,492.02 10. Reduction Amt to Escrow -1,316,410.00 0.00 11. Payment to Escrow 1,316,410.00 12. Net Pymt. this Estimate 27,492.02