Dept. of Trans. PROGRESS Serial No. Contract No. 11-083-10-15 08-4440U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 35% 08-SBD-215-8.8/11.6 Federal Project: NONE Progress payment No. 15 Payment period ending: 03-18-11 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 956600620 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,315,626.53 2,868,138.81 2.a. Extra Work 378,611.86 167,580.63 b. Adjustment Comp. 54,842.65 9,964.03 3. Materials on Hand 1,241,918.79 82,813.17 4. Earned Subject to Retention 32,990,999.83 3,128,496.64 5. Mobilization 6,687,827.00 334,391.35 6. Total Work Completed 38,436,908.04 7. Deductions -136,478.13 -6,750.69 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 39,542,348.70 3,456,137.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,456,137.30