Dept. of Trans. PROGRESS Serial No. Contract No. 11-237-15-09 08-4440U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 47% 08-SBD-215-8.8/11.6 Federal Project: NONE Progress payment No. 20 Payment period ending: 08-19-11 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 956600620 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 41,239,435.93 1,167,258.87 2.a. Extra Work 798,039.49 74,063.64 b. Adjustment Comp. 402,915.03 43,097.84 3. Materials on Hand 778,260.12 -37,019.90 4. Earned Subject to Retention 43,218,650.57 1,247,400.45 5. Mobilization 6,687,827.00 0.00 6. Total Work Completed 49,128,217.45 7. Deductions -136,478.13 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 49,769,999.44 1,247,400.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,247,400.45