Dept. of Trans. PROGRESS Serial No. Contract No. 13-025-13-06 08-4440U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 93% 08-SBD-215-8.8/11.6 Federal Project: NONE Progress payment No. 37 Payment period ending: 01-18-13 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 956600620 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 58,668,562.18 431,796.16 2.a. Extra Work 2,092,943.76 46,964.26 b. Adjustment Comp. 613,601.54 -197,437.20 3. Materials on Hand 4. Earned Subject to Retention 61,375,107.48 281,323.22 5. Mobilization 6,687,827.00 0.00 6. Total Work Completed 68,062,934.48 7. Deductions -147,209.13 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 67,915,725.35 281,323.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 281,323.22