Dept. of Trans. PROGRESS Serial No. Contract No. 04-174-14-01 08-446514 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 16% 08-RIV-71-0.0/2.7 Federal Project: HP21-6208(7) L-6208(7) Progress payment No. 05 Payment period ending: 06-16-04 SEMA CONSTRUCTION INC 2 SOUTH POINTE DRIVE STE 295 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,095,831.79 333,626.30 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 187,000.00 50,000.00 4. Earned Subject to Retention 2,282,831.79 383,626.30 5. Mobilization 721,000.25 0.00 6. Total Work Completed 2,816,832.04 7. Deductions -16,000.00 -6,000.00 8. a.Contract Retentions -162,827.60 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,825,004.44 377,626.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 377,626.30