Dept. of Trans. PROGRESS Serial No. Contract No. 14-329-07-12 08-448404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 83% 08-RIV-91-15.6/21.6 Federal Project: CMLN-6208(9) Progress payment No. 40 Payment period ending: 11-18-14 SEMA CONSTRUCTION INC 320 GODDARD WAY, SUITE 150 IRVINE, CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 78,337,321.97 2,376,690.55 2.a. Extra Work 1,938,459.06 0.00 b. Adjustment Comp. 1,373,170.84 133,749.86 3. Materials on Hand 854,273.48 -145,656.25 4. Earned Subject to Retention 82,503,225.35 2,364,784.16 5. Mobilization 4,117,000.00 0.00 6. Total Work Completed 85,765,951.87 7. Deductions -223,676.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 86,396,549.35 2,354,784.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,354,784.16