Dept. of Trans. PROGRESS Serial No. Contract No. 15-115-10-01 08-448404 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 95% Location: Federal Project: 08-RIV-91-15.6/21.6 CMLN-6208(9) Progress payment No. 045 Payment period ending: 04-20-15 SEMA CONSTRUCTION INC 320 GODDARD WAY, SUITE 150 IRVINE, CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 86,047,065.05 2,654,629.91 2. a. Extra Work 2,267,628.49 104,811.83 b. Adustment Comp. 3,307,931.74 176,741.28 3. Materials on Hand 656,658.42 -88,611.36 4. Earned Subject to Retention 92,279,283.70 2,847,571.66 5. Mobilization 4,117,000.00 0.00 6. Total Work Completed 95,739,625.28 7. Deductions -233,792.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 96,162,491.70 2,847,571.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,847,571.66