Dept. of Trans. PROGRESS Serial No. Contract No. 15-300-09-24 08-448404 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 100% Location: Federal Project: 08-RIV-91-15.6/21.6 CMLN-6208(9) Progress payment No. 053 Payment period ending: 10-20-15 SEMA CONSTRUCTION INC 320 GODDARD WAY, SUITE 150 IRVINE, CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 93,253,034.93 1,239,596.10 2. a. Extra Work 2,985,398.95 219,855.71 b. Adustment Comp. 4,135,710.36 35,295.68 3. Materials on Hand 181,925.05 -86,028.55 4. Earned Subject to Retention 100,556,069.29 1,408,718.94 5. Mobilization 4,117,000.00 0.00 6. Total Work Completed 104,491,144.24 7. Deductions -251,792.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 104,421,277.29 1,398,718.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,398,718.94