Dept. of Trans. PROGRESS Serial No. Contract No. 15-358-09-47 08-448404 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 97% Location: Federal Project: 08-RIV-91-15.6/21.6 CMLN-6208(9) Progress payment No. 055 Payment period ending: 12-17-15 SEMA CONSTRUCTION INC 320 GODDARD WAY, SUITE 150 IRVINE, CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 96,131,976.98 1,454,424.14 2. a. Extra Work 3,059,391.57 70,638.99 b. Adustment Comp. 4,033,557.42 -102,152.94 3. Materials on Hand 151,814.76 -6,695.36 4. Earned Subject to Retention 103,376,740.73 1,416,214.83 5. Mobilization 4,117,000.00 0.00 6. Total Work Completed 107,341,925.97 7. Deductions -271,792.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 107,221,948.73 1,406,214.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,406,214.83