Dept. of Trans. PROGRESS Serial No. Contract No. 16-119-08-28 08-448404 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 100% Location: Federal Project: 08-RIV-91-15.6/21.6 CMLN-6208(9) Progress payment No. 060 Payment period ending: 04-20-16 SEMA CONSTRUCTION INC 320 GODDARD WAY #150 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 98,947,241.78 1,139,154.02 2. a. Extra Work 3,855,525.19 202,197.51 b. Adustment Comp. 4,768,858.81 -239,146.01 3. Materials on Hand 4. Earned Subject to Retention 107,571,625.78 1,102,205.52 5. Mobilization 4,117,000.00 0.00 6. Total Work Completed 111,688,625.78 7. Deductions -291,792.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 111,396,833.78 1,102,205.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,102,205.52