Dept. of Trans. PROGRESS Serial No. Contract No. 16-175-08-58 08-448404 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 100% Location: Federal Project: 08-RIV-91-15.6/21.6 CMLN-6208(9) Progress payment No. 062 Payment period ending: 06-16-16 SEMA CONSTRUCTION INC 320 GODDARD WAY #150 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 100,138,532.70 923,110.40 2. a. Extra Work 4,447,164.54 0.00 b. Adustment Comp. 4,098,440.48 -735,003.97 3. Materials on Hand 4. Earned Subject to Retention 108,684,137.72 188,106.43 5. Mobilization 4,117,000.00 0.00 6. Total Work Completed 112,801,137.72 7. Deductions -291,792.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 112,509,345.72 188,106.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 188,106.43