Dept. of Trans. PROGRESS Serial No. Contract No. 16-266-12-28 08-448404 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 100% Location: Federal Project: 08-RIV-91-15.6/21.6 CMLN-6208(9) Progress payment No. 065 Payment period ending: 09-16-16 SEMA CONSTRUCTION INC 320 GODDARD WAY #150 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 100,994,790.54 6,194.69 2. a. Extra Work 4,728,793.24 33,020.23 b. Adustment Comp. 4,174,944.35 -1,838.51 3. Materials on Hand 4. Earned Subject to Retention 109,898,528.13 37,376.41 5. Mobilization 4,117,000.00 0.00 6. Total Work Completed 114,015,528.13 7. Deductions -301,136.10 -9,344.10 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 113,714,392.03 28,032.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 28,032.31