Dept. of Trans. PROGRESS Serial No. Contract No. 16-363-08-48 08-448404 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 100% Location: Federal Project: 08-RIV-91-15.6/21.6 CMLN-6208(9) Progress payment No. 068 Payment period ending: 12-18-16 SEMA CONSTRUCTION INC 320 GODDARD WAY #150 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 101,010,144.85 -187,302.20 2. a. Extra Work 5,062,561.01 290,076.77 b. Adustment Comp. 4,297,739.22 89,692.42 3. Materials on Hand 4. Earned Subject to Retention 110,370,445.08 192,466.99 5. Mobilization 4,117,000.00 0.00 6. Total Work Completed 114,487,445.08 7. Deductions -280,611.92 -38,819.92 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 114,206,833.16 153,647.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 153,647.07