Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 17-104-13-04 08-448404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-RIV-91-15.6/21.6 CMLN-6208(9) Progress payment No. 071 Payment period ending: 12-19-16 SEMA CONSTRUCTION INC 320 GODDARD WAY #150 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 101,113,413.87 10,743.20 2. a. Extra Work 5,553,852.04 337,032.04 b. Adustment Comp. 4,053,742.36 -230,284.23 3. Materials on Hand 4. Earned Subject to Retention 110,721,008.27 117,491.01 5. Mobilization 4,117,000.00 0.00 6. Total Work Completed 114,838,008.27 7. Deductions -289,491.48 -2,428.71 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 114,548,516.79 115,062.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 115,062.30