Dept. of Trans. PROGRESS Serial No. Contract No. 03-143-11-16 08-448504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 9% 9% 08-SBD-15-R21.3/R28.6 Federal Project: ACIM-015-1(216) ACIM-015-1(216) Progress payment No. 01 Payment period ending: 05-20-03 PAVE TECH INC 735 LAGUNA DRIVE CARLSBAD CA 92008-1651 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 246,901.80 246,901.80 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 122,534.09 122,534.09 4. Earned Subject to Retention 369,435.89 369,435.89 5. Mobilization 179,000.00 179,000.00 6. Total Work Completed 425,901.80 7. Deductions -4,800.00 -4,800.00 8. a.Contract Retentions -36,943.59 -36,943.59 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 506,692.30 506,692.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 506,692.30