Dept. of Trans. PROGRESS Serial No. Contract No. 03-175-13-16 08-448504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 21% 21% 08-SBD-15-R21.3/R28.6 Federal Project: ACIM-015-1(216) ACIM-015-1(216) Progress payment No. 02 Payment period ending: 06-17-03 PAVE TECH INC 735 LAGUNA DRIVE CARLSBAD CA 92008-1651 Escrow No. 02083 Total Estimate This Estimate 1. Contract Itms Without Mobil. 682,326.26 435,424.46 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 120,694.75 -1,839.34 4. Earned Subject to Retention 803,021.01 433,585.12 5. Mobilization 268,500.00 89,500.00 6. Total Work Completed 950,826.26 7. Deductions -14,800.00 -10,000.00 8. a.Contract Retentions -80,302.10 -43,358.51 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 976,418.91 469,726.61 10. Reduction Amt to Escrow 11. Payment to Escrow 80,300.00 12. Net Pymt. this Estimate 469,726.61