Dept. of Trans. PROGRESS Serial No. Contract No. 03-238-14-06 08-448504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 31% 49% 08-SBD-15-R21.3/R28.6 Federal Project: ACIM-015-1(216) ACIM-015-1(216) Progress payment No. 04 Payment period ending: 08-20-03 PAVE TECH INC 735 LAGUNA DRIVE CARLSBAD CA 92008-1651 Escrow No. 02083 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,119,085.48 344,025.13 2.a. Extra Work 1,981.07 1,981.07 b. Adjustment Comp. 3. Materials on Hand 120,694.75 -17,175.40 4. Earned Subject to Retention 1,241,761.30 328,830.80 5. Mobilization 340,100.00 0.00 6. Total Work Completed 1,461,166.55 7. Deductions -6,800.00 10,000.00 8. a.Contract Retentions -86,988.19 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,488,073.11 338,830.80 10. Reduction Amt to Escrow 11. Payment to Escrow 86,980.00 12. Net Pymt. this Estimate 338,830.80