Dept. of Trans. PROGRESS Serial No. Contract No. 03-297-10-52 08-448504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 35% 75% 08-SBD-15-R21.3/R28.6 Federal Project: ACIM-015-1(216) ACIM-015-1(216) Progress payment No. 06 Payment period ending: 10-20-03 PAVE TECH INC 735 LAGUNA DRIVE CARLSBAD CA 92008-1651 Escrow No. 02083 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,260,770.84 31,922.50 2.a. Extra Work 40,892.80 12,033.21 b. Adjustment Comp. 3. Materials on Hand 119,487.80 -1,206.95 4. Earned Subject to Retention 1,421,151.44 42,748.76 5. Mobilization 340,100.00 0.00 6. Total Work Completed 1,641,763.64 7. Deductions -4,800.00 0.00 8. a.Contract Retentions -86,988.19 0.00 b. Unsatisfactory Prog. -2,137.44 -2,137.44 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,667,325.81 40,611.32 10. Reduction Amt to Escrow 11. Payment to Escrow 86,980.00 12. Net Pymt. this Estimate 40,611.32