Dept. of Trans. PROGRESS Serial No. Contract No. 03-358-09-44 08-448504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 65% 95% 08-SBD-15-R21.3/R28.6 Federal Project: ACIM-015-1(216) ACIM-015-1(216) Progress payment No. 09 Payment period ending: 12-19-03 PAVE TECH INC 735 LAGUNA DRIVE CARLSBAD CA 92008-1651 Escrow No. 02083 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,650,558.16 964,217.20 2.a. Extra Work 108,648.57 0.00 b. Adjustment Comp. -3,372.48 0.00 3. Materials on Hand 119,487.80 0.00 4. Earned Subject to Retention 2,875,322.05 964,217.20 5. Mobilization 358,000.00 17,900.00 6. Total Work Completed 3,113,834.25 7. Deductions -4,800.04 0.00 8. a.Contract Retentions -143,766.10 -48,210.86 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,084,755.91 933,906.34 10. Reduction Amt to Escrow 11. Payment to Escrow 143,760.00 12. Net Pymt. this Estimate 933,906.34