Dept. of Trans. PROGRESS Serial No. Contract No. 04-056-16-16 08-448504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 81% 100% 08-SBD-15-R21.3/R28.6 Federal Project: ACIM-015-1(216) ACIM-015-1(216) Progress payment No. 11 Payment period ending: 02-20-04 PAVE TECH INC 735 LAGUNA DRIVE CARLSBAD CA 92008-1651 Escrow No. 02083 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,418,699.63 543,794.93 2.a. Extra Work 139,450.93 7,038.07 b. Adjustment Comp. -3,372.48 0.00 3. Materials on Hand 119,487.80 0.00 4. Earned Subject to Retention 3,674,265.88 550,833.00 5. Mobilization 358,000.00 0.00 6. Total Work Completed 3,912,778.08 7. Deductions -17,738.04 -9,338.00 8. a.Contract Retentions -183,713.29 -27,541.65 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,830,814.55 513,953.35 10. Reduction Amt to Escrow 11. Payment to Escrow 183,710.00 12. Net Pymt. this Estimate 513,953.35