Dept. of Trans. PROGRESS Serial No. Contract No. 04-085-11-26 08-448504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 100% 08-SBD-15-R21.3/R28.6 Federal Project: ACIM-015-1(216) ACIM-015-1(216) Progress payment No. 12 Payment period ending: 03-19-04 PAVE TECH INC 735 LAGUNA DRIVE CARLSBAD CA 92008-1651 Escrow No. 02083 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,880,704.86 462,005.23 2.a. Extra Work 207,299.32 67,848.39 b. Adjustment Comp. -2,687.94 684.54 3. Materials on Hand 46,560.50 -72,927.30 4. Earned Subject to Retention 4,131,876.74 457,610.86 5. Mobilization 358,000.00 0.00 6. Total Work Completed 4,443,316.24 7. Deductions -118,007.52 -100,269.48 8. a.Contract Retentions -206,593.84 -22,880.55 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,165,275.38 334,460.83 10. Reduction Amt to Escrow 11. Payment to Escrow 206,590.00 12. Net Pymt. this Estimate 334,460.83