Dept. of Trans. PROGRESS Serial No. Contract No. 04-117-14-06 08-448504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 100% 08-SBD-15-R21.3/R28.6 Federal Project: ACIM-015-1(216) ACIM-015-1(216) Progress payment No. 13 Payment period ending: 04-20-04 PAVE TECH INC 735 LAGUNA DRIVE CARLSBAD CA 92008-1651 Escrow No. 02083 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,969,578.92 88,874.06 2.a. Extra Work 218,476.13 11,176.81 b. Adjustment Comp. -2,687.94 0.00 3. Materials on Hand 0.00 -46,560.50 4. Earned Subject to Retention 4,185,367.11 53,490.37 5. Mobilization 358,000.00 0.00 6. Total Work Completed 4,543,367.11 7. Deductions -41,166.43 76,841.09 8. a.Contract Retentions -209,268.36 -2,674.52 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,292,932.32 127,656.94 10. Reduction Amt to Escrow 11. Payment to Escrow 209,260.00 12. Net Pymt. this Estimate 127,656.94