Dept. of Trans. SEMI-FINAL Serial No. Contract No. 04-309-17-07 08-448504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 08-SBD-15-R21.3/R28.6 Federal Project: ACIM-015-1(216) ACIM-015-1(216) Progress payment No. 17 Payment period ending: 04-30-04 PAVE TECH INC 735 LAGUNA DRIVE CARLSBAD CA 92008-1651 Escrow No. 02083 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,948,925.01 -16,333.38 2.a. Extra Work 431,021.09 101,576.26 b. Adjustment Comp. 149,822.86 12,248.41 3. Materials on Hand 4. Earned Subject to Retention 4,529,768.96 97,491.29 5. Mobilization 358,000.00 0.00 6. Total Work Completed 4,887,768.96 7. Deductions -81,755.91 15,692.92 8. a.Contract Retentions -209,268.36 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 209,268.36 0.00 9. Total pay to Contractor 4,806,013.05 113,184.21 10. Reduction Amt to Escrow -209,260.00 0.00 11. Payment to Escrow 209,260.00 12. Net Pymt. this Estimate 113,184.21