Dept. of Trans. PROGRESS Serial No. Contract No. 12-173-09-49 08-449314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 43% 35% 08-RIV-215-R38.0/38.9 Federal Project: ACNH-X065(95) CMLN-6208(17) Progress payment No. 15 Payment period ending: 06-14-12 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA SUITE 200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,814,841.16 770,015.38 2.a. Extra Work 236,780.60 124,164.46 b. Adjustment Comp. 124,534.96 6,468.61 3. Materials on Hand 223,774.83 -27,945.72 4. Earned Subject to Retention 8,399,931.55 872,702.73 5. Mobilization 2,087,401.56 0.00 6. Total Work Completed 10,263,558.28 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,477,333.11 872,702.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 872,702.73