Dept. of Trans. PROGRESS Serial No. Contract No. 13-205-17-00 08-449314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 74% 08-RIV-215-R38.0/38.9 Federal Project: ACNH-X065(95) CMLN-6208(17) Progress payment No. 28 Payment period ending: 07-18-13 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA SUITE 200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,443,522.74 341,200.29 2.a. Extra Work 437,122.16 4,432.45 b. Adjustment Comp. 424,719.86 0.00 3. Materials on Hand 32,352.25 -5,675.84 4. Earned Subject to Retention 17,337,717.01 339,956.90 5. Mobilization 2,197,264.80 0.00 6. Total Work Completed 19,502,629.56 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,524,981.81 339,956.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 339,956.90