Dept. of Trans. PROGRESS Serial No. Contract No. 05-206-13-45 08-451404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 95% 08-SBD-18-36.2/37.3 Federal Project: ACST-P018(36) PH-P018(36) Progress payment No. 03 Payment period ending: 07-20-05 PK CONSTRUCTION 2255 N WINDSOR ALTADENA CA 91001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 261,554.25 150,231.25 2.a. Extra Work 76,674.66 5,574.50 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 338,228.91 155,805.75 5. Mobilization 6. Total Work Completed 338,228.91 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 338,228.91 155,805.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 155,805.75