Dept. of Trans. PROGRESS Serial No. Contract No. 09-147-14-05 08-452204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 71% 08-RIV-15-40.0/40.7 Federal Project: STPL-5104(32) N-5104(32) Progress payment No. 17 Payment period ending: 05-20-09 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIRCLE CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,600,984.87 812,481.36 2.a. Extra Work 418,814.48 7,871.37 b. Adjustment Comp. -36,799.99 507.89 3. Materials on Hand 45,931.79 0.00 4. Earned Subject to Retention 11,028,931.15 820,860.62 5. Mobilization 1,106,920.00 0.00 6. Total Work Completed 12,089,919.36 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,135,851.15 820,860.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 820,860.62